To find plaster volume, multiply the net wall area in m² by the coat thickness in metres. An 18 m² wall area with a 15 mm coat needs 0.270 m³, or 270 L. Use the chosen product’s consumption rate to estimate the dry mix in kilograms.
Plaster volume starts with the net area
Subtract the openings that you will leave unplastered from the wall area. If you plan to plaster the reveals, measure and add their area separately. Where the coat varies in thickness, add the volumes of individual sections, as in the example of dividing an uneven wall into zones.
Divide the thickness in millimetres by 1,000 to get metres. Multiply the area by this value using the NIST rectangular volume formula. If you need litres, a 1 mm coat over 1 m² takes up 1 L.
Worked example for a wall with a doorway
Take a wall with an area of 20 m² and a doorway of 2 m². Assume a uniform 15 mm coat and leave out the reveals and any waste allowance.
Net area: 20 − 2 = 18 m². Thickness: 15 ÷ 1,000 = 0.015 m.
Coat volume: 18 × 0.015 = 0.270 m³, or 270 L.
How to work out how many bags to buy
The weber.dur 110 technical data sheet lists about 19 kg/m² at 15 mm and 30 kg bags for this lime-cement render. The estimated dry mix needed is 18 × 19 = 342 kg. Divide by the bag weight: 342 ÷ 30 = 11.4, then round up to 12 bags before any waste allowance.
Different products can require different amounts of dry mix for the same coat volume. For another mix, use the consumption rate from its data sheet for your thickness. If needed, add a waste allowance once, before rounding to whole bags.
How to check the volume in Budova
Select metric units in Settings if needed, then enter an area of 18 m² and a thickness of 15 mm. The base calculation gives a coat volume of 0.270 m³. The cement and sand estimates depend on the selected mix proportions for cement-sand mortar. For a bagged dry mix, use its data sheet and the bag calculation above.