Screed volume equals the floor area multiplied by the average layer thickness in meters. For an area of 20 m² and a 50 mm layer, this is 20 × 0.05 = 1 m³. This is a geometric volume, not a ready-made count of bags of dry mix.
Screed volume: convert the thickness to meters
Divide millimeters by 1000. A 40 mm layer equals 0.04 m, 50 mm equals 0.05 m, and 60 mm equals 0.06 m. Multiplying the area by 50 instead of 0.05 overstates the result by a factor of a thousand.
Room: 5 × 4 = 20 m².
Average thickness: 50 ÷ 1000 = 0.05 m.
Volume: 20 × 0.05 = 1 m³.
Illustrative 5% allowance: 1 × 1.05 = 1.05 m³.
The 5% allowance here only demonstrates the arithmetic. The selected percentage does not compensate for an incorrect measurement of variations in the base level. Establish the consumption rate and installation method for the specific material.
What an extra 10 mm changes
For the same area, a 60 mm layer gives 20 × 0.06 = 1.2 m³. The difference from a 50 mm layer is 0.2 m³, or 20% of the original volume. Measuring thickness therefore affects purchasing more than rounding the final digit.
For several rooms there is a separate guide: screed in several rooms.
If the base is uneven, do not use the minimum thickness as the average for the entire room. Measure at several points and divide the floor into zones. Calculate each zone's area and average thickness separately, then add the volumes.
Cubic meters are not bags
For dry mix, use the consumption rate stated by the manufacturer. If it is given in kg/m² per 1 mm of layer thickness, multiply it by the area and thickness in millimeters. Then divide the mass by the bag weight and round up.
To compare offers in different units, see cement price per bag and per tonne.
For example, with an illustrative consumption rate of 2 kg/m² per 1 mm, 20 m² at 50 mm requires 2000 kg. With 25 kg bags, this is 80 bags without an allowance. The number 2 is an educational assumption, not a specification for a particular mix.
Do not apply one mix's consumption rate to another. Do not estimate the composition of cement-sand mortar from the geometric volume without the component properties and required mix proportions.
The floor construction determines the thickness
This article calculates the amount of material and does not specify a layer thickness. The type of base, floor system, and manufacturer's instructions determine the permissible thickness. For example, Ceresit CN 178 has its own application requirements. Consult the current technical data sheet for your specific product.
In Budova, open the screed volume calculation and enter the area and measured thickness. Make sure that the units are correct before transferring the result to your order.